Lift inspection time standarization

March 2009 - July 2009

Funding entity THYSSENKRUPP ELEVADORES S.A.

Participated by ATISAE


Lift inspection by ThyssenKrupp company requires a different checking activity list depending on several factors such as Model type, stops number, type of inspection, lift configuration and type of building.
At this project lift revision time standardization has been done to evaluate the impact of previous factors. To deal with standardization process a revision sampling scheme has been coordinated with the Company and also a specific sampling time pattern has been elaborated for time analysts. Finally this project analyses revision samples to elaborate a standard revision time model.